Essilor International SAS v. J.P. Morgan Chase Bank, N.A.
- Lewis Liman
- 1:22-cv-03361
- U.S. District Court · Southern District of New York
- 3
In Essilor v. J.P. Morgan, Judge Liman denied Essilor’s request to strike JPMC’s damages expert report and partly granted related sealing motions.
Essilor Mfg. (Thailand) Co., Ltd., J.P. Morgan Chase Bank, N.A., and the experts whose reports were addressed by the motions. The order also affected whether portions of the expert reports would remain publicly accessible.
What happened
In Essilor International SAS v. J.P. Morgan Chase Bank, N.A., Essilor Mfg. (Thailand) Co., Ltd. asked the court to strike J.P. Morgan Chase Bank’s damages expert report as late. J.P. Morgan served the report on the deadline for rebuttal reports, after Essilor had not served a damages report.
The court did not decide whether the report complied with the scheduling order. Instead, it found that excluding the report would be too severe because J.P. Morgan had a reasonable explanation, the report addressed an important issue, Essilor could depose the expert, and no trial date had been set. The court also allowed Essilor to seek permission to use a damages rebuttal expert by letter motion.
Judge Liman denied Essilor’s motion to strike. He denied the motions to file the Deetz Report in redacted form to the extent they sought to redact paragraph 14, but otherwise granted them as to that report. The motions concerning the reports of Richard M. Fraher and Terri Sands were denied without prejudice, and the documents remained sealed while J.P. Morgan could seek renewed sealing relief.
The detailed version
- Essilor International SAS v. J.P. Morgan Chase Bank, N.A. · No. 1:22-cv-03361
- Lewis Liman
- Aug. 22, 2024
Background
Plaintiff Essilor Mfg. (Thailand) Co., Ltd. moved to strike the expert report of Gene L. Deetz, which J.P. Morgan Chase Bank, N.A. offered on damages. Essilor argued that the report was an untimely opening report because J.P. Morgan served it on the deadline for rebuttal reports rather than the deadline for opening reports. Essilor had served two expert reports concerning liability but had not served a damages report.
The scheduling order required the parties to identify testifying experts and exchange opening reports by June 28, 2024; identify rebuttal experts and exchange rebuttal reports by July 30, 2024; and exchange reply reports by August 29, 2024. Expert discovery was due to be completed by September 27, 2024, and summary-judgment motions were due by October 25, 2024.
J.P. Morgan argued that the Deetz Report was timely because it responded to assumptions in the report of Essilor’s liability expert, Richard M. Fraher. It also argued that it understood it would not need to submit a damages report until after Essilor submitted one, because Essilor had the burden of proving damages. The parties disagreed about whether exclusion of the report was appropriate if it was late.
Court’s Analysis
The court said it did not need to decide whether J.P. Morgan’s service of the Deetz Report complied with the scheduling order. Excluding an expert’s testimony is a severe remedy that courts generally disfavor. Under the factors identified in Softel, courts consider the explanation for the disclosure failure, the importance of the testimony, the prejudice to the opposing party, and whether a continuance is possible. Courts must also consider less severe responses before excluding the testimony.
The court found that these factors weighed against exclusion. J.P. Morgan had a reasonable explanation: it expected Essilor to submit a damages report and believed its own report would be due as a rebuttal report. The Deetz Report also responded, at least in part, to assumptions underlying Fraher’s analysis. The court considered the report important because it addressed the remedy if Essilor proved liability. It rejected Essilor’s argument that the damages calculation was not complex or that a nonexpert witness could easily provide the analysis. Any prejudice to Essilor could be reduced by allowing Essilor to depose Deetz. Because no trial date had been set, a short continuance would not interfere with the case’s ultimate resolution.
The court stated that it would consider a letter motion from Essilor seeking to use a damages rebuttal expert and further extend discovery, provided the parties first met and conferred and the motion was filed by August 30, 2024.
Rulings
The motion at Dkt. No. 167 to strike the Deetz Report was denied.
The motions at Dkt. Nos. 166 and 172 to file the Deetz Report in redacted form were denied to the extent they sought to redact the information in paragraph 14 of Dkt. No. 173-1 and were otherwise granted with respect to the Deetz Report. J.P. Morgan was directed to file a redacted version consistent with the order by August 26, 2024.
The motions at Dkt. Nos. 166 and 172 were denied without prejudice with respect to the reports of Richard M. Fraher and Terri Sands. The Clerk was directed to keep the related documents under seal so J.P. Morgan could file a renewed sealing motion under the standards governing public access to court records. If no renewed motion was filed by August 26, 2024, the court stated that it would direct that two of the documents be unsealed. The court also noted that the presumption of public access could become stronger if the reports were later used with summary judgment or at trial.
The Clerk was directed to close the motions at Dkt. Nos. 166, 167, 169, and 172. The order was signed by Judge Lewis J. Liman on August 22, 2024.
Read the full 3-page opinion on CourtListener, the free public archive maintained by the Free Law Project.