PG&E Corporation v. AECOM Technical Services, Inc..
- Haywood Gilliam
- 4:20-cv-05381
- U.S. District Court · Northern District of California
- 8
In JH Kelly v. AECOM, Judge Gilliam dismissed five counterclaims with leave to amend and dismissed a mechanics-lien claim without leave.
AECOM’s counterclaims against PG&E were dismissed in part. AECOM may amend the five claims dismissed with leave to amend, but its mechanics’-lien claim was dismissed without leave to amend. PG&E’s motion was granted in part; the opinion does not state a separate disposition for the remaining claims.
What happened
JH Kelly, LLC v. AECOM Technical Services, Inc. is a construction dispute involving a project to replace and upgrade equipment at a natural-gas compressor station. AECOM asserted claims against PG&E and JH Kelly, and PG&E asked the court to dismiss several of AECOM’s non-contract claims.
The court granted PG&E’s motion to dismiss in part. It dismissed AECOM’s claims for negligent misrepresentation and fraudulent concealment because AECOM did not identify the alleged false statements with the detail required for fraud-based claims. It also dismissed AECOM’s claims for quantum meruit, implied contractual indemnity, and contribution or apportionment because the counterclaim did not adequately plead those claims. The court allowed AECOM to amend those claims. Separately, it dismissed AECOM’s claim concerning the priority and extent of its mechanics’ lien without leave to amend, based on the parties’ stipulation and an earlier ruling.
Judge Haywood S. Gilliam, Jr. ordered that any amended counterclaim be filed within 21 days and barred AECOM from adding new claims or defendants. The opinion’s discussion identifies implied contractual indemnity as the eighth cause of action, while its conclusion refers to the ninth cause of action; both sections identify the claim as dismissed with leave to amend.
The detailed version
- PG&E Corporation v. AECOM Technical Services, Inc.. · No. 4:20-cv-05381
- Haywood Gilliam
- June 28, 2021
Background
The dispute arises from the Burney K2 Replacement Project, which involved replacing a natural-gas compressor unit and making upgrades at a compressor station. PG&E and AECOM entered into an engineering, procurement, and construction agreement. AECOM then subcontracted construction obligations to JH Kelly, LLC. The parties disputed responsibility for alleged delays, cost overruns, contractual violations, and tortious conduct.
AECOM’s First Amended Counterclaim asserted sixteen causes of action against PG&E and JH Kelly. PG&E moved under Federal Rule of Civil Procedure 12(b)(6), which permits dismissal when a pleading does not state a legally sufficient claim. The motion concerned AECOM’s non-contract claims against PG&E: negligent misrepresentation, fraudulent concealment, quantum meruit, implied contractual indemnity, and contribution or apportionment.
Negligent Misrepresentation and Fraudulent Concealment
AECOM based these claims on alleged representations in PG&E’s request for proposal. AECOM alleged that PG&E represented that it would make only minimal changes to the pre-bid design, that the design was accurate, that the construction methods were described in the request for proposal, and that the project and design scope would be fixed at the pre-bid stage, subject to schedule extensions or price increases for later changes.
Because these claims sounded in fraud under California law, the court applied Federal Rule of Civil Procedure 9(b). That rule requires fraud to be pleaded with particularity, including the time, place, specific content, and participants in the alleged misrepresentation. The court found that AECOM had not identified the specific provisions of the request for proposal containing the alleged misrepresentations or provided sufficient context for them. The court therefore dismissed both claims with leave to amend. It did not decide PG&E’s separate argument concerning California’s economic-loss rule.
Quantum Meruit
Quantum meruit is a theory for recovering the reasonable value of services when a contract does not govern the recovery. AECOM alleged that PG&E’s excessive project changes amounted to abandonment of the construction agreement and entitled AECOM to recover under quantum meruit.
The court explained that abandonment requires both parties to intend to disregard the contract. AECOM alleged facts that might show PG&E’s implied intent to abandon the agreement, including demands for numerous changes and failure to follow the agreement’s change-order process. But AECOM did not allege that it also intended to abandon the agreement. The court noted that AECOM’s other claims sought to enforce the same agreement. It dismissed the quantum meruit claim with leave to amend.
Implied Contractual Indemnity
AECOM sought implied contractual indemnity if it were found derivatively liable to JH Kelly. The court held that California law requires a joint legal obligation to the injured party for an implied contractual indemnity claim. AECOM did not plausibly allege that PG&E and AECOM shared such an obligation to JH Kelly. The court dismissed this claim with leave to amend.
Contribution or Apportionment
AECOM’s contribution or apportionment claim appeared to depend on its implied contractual indemnity theory, and AECOM offered no other basis for the claim’s viability. The court therefore dismissed the contribution or apportionment claim against PG&E with leave to amend.
Other Dispositions and Order
The opinion states that the parties stipulated to dismissal of AECOM’s claim for determination of the priority and extent of its mechanics’ lien against PG&E, based on the court’s prior ruling on JH Kelly’s mechanics’ lien foreclosure claim. The court dismissed that first cause of action without leave to amend.
The order granted PG&E’s motion to dismiss in part. The body of the opinion identifies the dismissed claims with leave to amend as the fifth, sixth, seventh, eighth, and sixteenth causes of action. The conclusion instead refers to the fifth, sixth, seventh, ninth, and sixteenth causes of action. The order allowed AECOM 21 days from the order’s date to file an amended counterclaim and prohibited it from adding new causes of action or defendants. The request for judicial notice was denied as moot because the court did not rely on the submitted documents.
Read the full 8-page opinion on CourtListener, the free public archive maintained by the Free Law Project.