Engineering & Construction Innovations, Inc. v. Bradshaw Construction Corp.
- Eric Tostrud
- 0:20-cv-00808
- U.S. District Court · District of Minnesota
- 9
Engineering & Construction Innovations v. Bradshaw Construction, Judge Leung, granted ECI’s motion to amend its complaint to add an indemnification claim.
Engineering & Construction Innovations, Inc. may add its proposed indemnification-related breach-of-contract claim against Bradshaw Construction Corporation; the order did not decide the claim’s ultimate merits.
What happened
Engineering & Construction Innovations, Inc. v. Bradshaw Construction Corporation involved ECI’s request to add a claim that Bradshaw breached its contract by refusing to defend and indemnify ECI in a related lawsuit. ECI alleged that Bradshaw’s defective work caused flooding and delays on a Minneapolis water-main project.
Bradshaw argued that the proposed claim was futile because the contract did not require indemnification for declaratory-judgment actions and because ECI’s interpretation would be unlawful or absurd. The court said those issues could not be resolved at this stage because the relevant insurance policy, business practices, and liability questions were not adequately before it.
The court granted ECI’s motion to amend its complaint and ordered ECI to file the amended complaint within 14 days. The order was signed by Magistrate Judge Tony N. Leung.
The detailed version
- Engineering & Construction Innovations, Inc. v. Bradshaw Construction Corp. · No. 0:20-cv-00808
- Eric Tostrud
- Sept. 3, 2020
Background
Engineering & Construction Innovations, Inc. (ECI) was the general contractor for a City of Minneapolis project to install a water main under the Mississippi River near the 10th Avenue Bridge. ECI hired Bradshaw Construction Corporation as a subcontractor for microtunneling work. The contract required Bradshaw to defend, indemnify, and hold harmless ECI and Minneapolis from claims, damages, and expenses resulting from specified misconduct, omissions, negligent acts, or third-party claims arising from Bradshaw’s breach of the contract. Bradshaw also obtained a performance bond from Travelers Casualty & Surety Company of America.
ECI alleged that Bradshaw’s defective work caused two floods and substantial delay, that Bradshaw completed only 70 of the required 896 feet of tunneling, and that Bradshaw later entered the work site without permission and caused another flood. After Minneapolis required ECI to terminate Bradshaw and remove it from the project, ECI did so and asked Travelers to perform under the bond. Travelers refused. The related lawsuits were consolidated in this matter.
ECI then asked Bradshaw to defend and indemnify ECI in the Travelers lawsuit. ECI alleged that Bradshaw failed or declined to do so and sought to amend its complaint to add a breach-of-contract claim based on that alleged failure.
Motion to Amend
Under Federal Rule of Civil Procedure 15, a party generally needs the opposing party’s consent or the court’s permission to amend a pleading after the applicable period for amendment as of right has passed. Courts ordinarily allow amendments unless there are compelling reasons such as undue delay, bad faith, prejudice, repeated failure to correct deficiencies, or futility.
Bradshaw argued that the proposed indemnification claim was futile. A proposed amendment is futile if it could not survive a motion to dismiss for failure to state a claim under Rule 12(b)(6). Applying Minnesota law, the court explained that a breach-of-contract claim requires allegations showing an agreement, performance of conditions required before demanding performance, and breach.
The court determined that ECI had alleged those elements by pointing to the contract’s indemnification clause, alleging that ECI had performed the relevant conditions, and alleging that Bradshaw refused to indemnify ECI.
Indemnification Arguments
Bradshaw argued that the indemnification clause did not cover declaratory-judgment actions. The court observed that the clause covered “all claims” and “expenses,” including reasonable attorney’s fees, and that its language was broad enough to include a declaratory-judgment action and attorney’s fees ECI incurred defending such an action.
Bradshaw also argued that the contract’s insurance provisions limited its indemnification obligations. The court declined to resolve that issue because ECI’s proposed complaint did not identify the relevant commercial general liability policy or allege facts showing whether such policies ordinarily cover declaratory-judgment actions. Bradshaw had not asked the court to take judicial notice of the policy. The court likewise found that the contract’s separate insurance provision was silent on whether it limited the broad indemnification language. Discovery about the policies and the parties’ ordinary business practices could bear on that issue.
Bradshaw further argued that ECI’s interpretation would produce an absurd and unenforceable result because Bradshaw would have to defend ECI while taking a position contrary to its own litigation position. The court explained that Minnesota law limits construction-contract indemnification provisions when the claimed damage is not attributable to the promisor’s own wrongful conduct. But the court found the argument premature because liability between ECI and Bradshaw had not yet been decided. The court stated that it could manage the litigation so the parties’ rights under the indemnification clause would not be foreclosed and Bradshaw would not be forced to take legally inconsistent positions.
Disposition
The court GRANTED ECI’s Motion to Amend Complaint. It ordered ECI to file the amended complaint within 14 days of the order. The ruling allowed ECI to add the indemnification-related breach-of-contract claim; it did not decide whether Bradshaw ultimately owed indemnification or whether ECI would prevail on that claim.
Read the full 9-page opinion on CourtListener, the free public archive maintained by the Free Law Project.