Court, Explained
U.S. Federal District Courts
Back to docket
D. Minn.Procedural orderFiled July 12, 2021

Richard Goettle, Inc. v. Kevitt Excavating, LLC

Judge
Tony Leung
Docket
0:20-cv-02068
Court
U.S. District Court · District of Minnesota
Pages
8
Civil ProcedureContractMotion to Dismiss
In one sentence

In Richard Goettle v. Kevitt Excavating, Judge Wright granted in part and denied in part Goettle’s motion to dismiss Kevitt’s counterclaims.

Who this affects

Richard Goettle, Inc. and Kevitt Excavating, LLC; Kevitt’s equitable-relief counterclaim was dismissed, while its two breach-of-contract counterclaims, offset counterclaim, and declaratory-judgment counterclaim survived the motion to dismiss.

What happened

Richard Goettle, Inc. sued Kevitt Excavating, LLC, alleging disputes arising from a drilling subcontract on a Minneapolis construction project. Kevitt responded with five counterclaims, including breach of contract, offset, equitable relief, and declaratory judgment.

Goettle asked the court to dismiss all of Kevitt’s counterclaims for failing to state legally sufficient claims. The court concluded that Kevitt adequately alleged damages for its contract claims, could pursue its offset claim, and had a sufficient basis for declaratory judgment. But the court ruled that equitable relief was unavailable because a valid contract governed the parties’ relationship.

The court granted in part and denied in part Goettle’s motion to dismiss. Judge Wright granted the motion as to Kevitt’s equitable-relief counterclaim and denied it as to the two contract counterclaims, the offset counterclaim, and the declaratory-judgment counterclaim.

The detailed version

For law students, journalists, and other readers who want the full reasoning

Case
Richard Goettle, Inc. v. Kevitt Excavating, LLC · No. 0:20-cv-02068
Judge
Tony Leung
Date
July 12, 2021

Background

The City of Minneapolis hired Kevitt Excavating, LLC to perform excavation work on a downtown Minneapolis construction project. Richard Goettle, Inc. later entered into a subcontract with Kevitt to perform drilling work. After delays and payment disputes involving Kevitt, the project construction manager, and Goettle, Goettle sued Kevitt and Granite Re, Inc., Kevitt’s payment-bond surety, in Ohio state court.

Kevitt filed an answer and asserted five counterclaims against Goettle: two for breach of contract, one for offset and setoff, one seeking equitable relief, and one seeking a declaratory judgment. The case was removed to federal court in Ohio and then transferred to the District of Minnesota. The opinion states that the subcontract was signed in January 2019 and notes that the complaint’s reference to January 2018 appeared to be a typographical error.

Legal Standard

Goettle moved under Federal Rule of Civil Procedure 12(b)(6), which allows dismissal when a pleading does not state a legally sufficient claim for relief. At this stage, the court generally treats well-pleaded factual allegations as true and asks whether they plausibly support relief.

Breach of Contract: Counts I and II

Goettle argued that Kevitt’s contract counterclaims failed because Kevitt had not alleged damages. The court agreed that damages are an element of a breach-of-contract claim under Minnesota law. But the court concluded that Kevitt had plausibly alleged damages, including damages exceeding $500,000 on one claim and $75,000 on the other. Kevitt also alleged damages related to project delays, Goettle’s alleged failure to contribute meaningfully to negotiations and settlement with the City, and Goettle’s alleged refusal to honor defense and indemnity obligations.

The court therefore denied Goettle’s motion to dismiss Counterclaim Counts I and II.

Offset and Setoff: Count III

Kevitt alleged that it had contractual and common-law rights to offset amounts it believed Goettle owed against amounts Goettle claimed Kevitt owed. Goettle argued that offset could not be asserted as an independent counterclaim. The court found no legal rule preventing such a counterclaim and concluded that Kevitt’s allegations were sufficient at the pleading stage.

The court therefore denied Goettle’s motion to dismiss Counterclaim Count III.

Equitable Relief: Count IV

Kevitt sought an order requiring Goettle to defend and indemnify Kevitt for $412,500 allegedly withheld from Kevitt’s contract with the City, along with attorneys’ fees, expenses, and expert fees. Goettle argued that equitable relief was unavailable because a contract governed the parties’ relationship.

The court granted Goettle’s motion to dismiss Counterclaim Count IV. It reasoned that equitable relief is unavailable when an adequate legal remedy exists and the parties’ rights are governed by a valid contract. At the hearing, counsel for both parties confirmed that a valid contract existed.

Declaratory Judgment: Count V

Goettle argued that Kevitt’s declaratory-judgment counterclaim should be dismissed because no viable claim remained between the parties. The court rejected that argument because Kevitt’s breach-of-contract counterclaims survived dismissal. The court therefore denied Goettle’s motion to dismiss Counterclaim Count V.

Disposition

The order states that Goettle’s motion to dismiss is granted in part and denied in part. The motion is granted as to Kevitt’s Counterclaim Count IV and denied as to Counterclaim Counts I, II, III, and V.

The authoritative version

Read the full 8-page opinion on CourtListener, the free public archive maintained by the Free Law Project.

Open opinion PDF →
Summary written with AI assistance. See how summaries are made. Spot something wrong? Tell us.