Court, Explained
U.S. Federal District Courts
Back to docket
D. Minn.Procedural orderFiled Aug. 13, 2021

Southern Minnesota Beet Sugar Cooperative v. Agri Systems

Judge
Elizabeth Cowan Wright
Docket
0:17-cv-05552
Court
U.S. District Court · District of Minnesota
Pages
8
Civil ProcedureContract
In one sentence

In Southern Minnesota Beet Sugar Cooperative v. Agri Systems, Judge Wright partly granted and partly denied the motion: contract claims go to a bench trial, negligence to a jury.

Who this affects

Southern Minnesota Beet Sugar Cooperative and Agri Systems; the ruling determines that the contract claims will be tried by the judge and the professional-negligence claim by a jury.

What happened

Southern Minnesota Beet Sugar Cooperative sued Agri Systems over the design and construction of an industrial sugar-storage facility. After equipment allegedly failed, the cooperative sought $3.3 million in damages. The remaining claims were three contract claims and one professional-negligence claim.

Agri Systems had asked for a jury trial but later sought to withdraw that request. The parties agreed that their contract included a jury-trial waiver, but they disagreed about whether it applied to every remaining claim. The cooperative did not agree to waive a jury trial for the professional-negligence claim.

Judge Wilhelmina M. Wright granted the motion in part and denied it in part. Agri Systems could withdraw its jury demand for the contract claims, which will be tried by the judge, but it could not withdraw the demand for the professional-negligence claim, which will be tried by a jury. The court said the claims would be split between those two trials unless the cooperative agrees to a judge-only trial for all claims.

The detailed version

For law students, journalists, and other readers who want the full reasoning

Case
Southern Minnesota Beet Sugar Cooperative v. Agri Systems · No. 0:17-cv-05552
Judge
Elizabeth Cowan Wright
Date
Aug. 13, 2021

Background

Southern Minnesota Beet Sugar Cooperative (SMBSC) sued Agri Systems, doing business as ASI Industrial, Inc. (ASI), concerning the design and construction of six concrete sugar silos. SMBSC alleged that part of the equipment failed after construction and sought $3.3 million in damages.

SMBSC originally asserted six claims. The court had already granted summary judgment to ASI on Counts IV and VI. The claims remaining in this order were Counts I, II, and III—contract, express-warranty, and implied-warranty claims—and Count V, professional negligence.

The parties’ Design-Build Agreement included a provision waiving jury trials for disputes arising from or relating to the agreement and its related documents. Despite that provision, ASI demanded a jury trial in its answer. ASI later moved to withdraw its jury demand as to all remaining claims. SMBSC opposed the motion.

Contract Claims

The court held that the contractual jury-trial waiver was knowing and voluntary and therefore enforceable as to Counts I, II, and III. In reaching that conclusion, the court considered that the parties negotiated the agreement, exchanged revisions to the jury-waiver language, were represented by counsel, and were sophisticated business entities. The waiver was also set out in a separately labeled paragraph, and the record did not show unequal bargaining power or a lack of opportunity to review the agreement.

Because the waiver was valid, the court concluded that ASI’s jury demand was improper as to the contract claims. The court therefore allowed ASI to withdraw its jury demand for Counts I, II, and III.

Professional-Negligence Claim

The parties agreed that the jury waiver did not apply to Count V. The court relied on its earlier summary-judgment ruling that SMBSC’s professional-negligence claim was an independent tort that did not arise from the Design-Build Agreement.

Because the waiver did not cover Count V, ASI’s jury demand was proper for that claim. Under Federal Rule of Civil Procedure 38(d), ASI could not withdraw the demand without SMBSC’s consent. SMBSC did not consent, so the professional-negligence claim will proceed to a jury trial.

Disposition

The court ordered that ASI’s motion to withdraw its jury-trial demand was granted in part and denied in part. Unless SMBSC consents to a judge-only trial on all claims, the court will hold a bench trial—meaning a trial decided by the judge—on Counts I, II, and III, and a jury trial on Count V.

The authoritative version

Read the full 8-page opinion on CourtListener, the free public archive maintained by the Free Law Project.

Open opinion PDF →
Summary written with AI assistance. See how summaries are made. Spot something wrong? Tell us.