Woodland Creek Manor Homes Association, Inc. v. AmGUARD Insurance Company
- Eric Tostrud
- 0:20-cv-01833
- U.S. District Court · District of Minnesota
- 15
In Woodland Creek v. AmGUARD, Judge Tostrud granted in part both parties’ summary-judgment motions, ruling on replacement costs and interest.
Woodland Creek Manor Homes Association, Inc. and AmGUARD Insurance Company; the ruling determines how the covered hail-loss replacement costs and pre-award interest are calculated under their insurance policy and Minnesota law.
What happened
Woodland Creek Manor Homes Association’s property suffered covered hail damage, but it and AmGUARD Insurance Company disagreed about how to calculate replacement costs and interest. Both parties asked the court to decide those issues without a trial.
The court ruled that replacement-cost value must use the cost when repairs were made or the pricing used at the appraisal, not the cost when the storm occurred. It also ruled that pre-award interest does not apply to amounts AmGUARD paid before the appraisal from the dates of those payments, and that interest on the replacement-cost portion can be recovered only after the covered repairs are completed. Both parties’ motions for partial summary judgment were granted in part and denied in all other respects.
Judge Eric C. Tostrud issued the ruling under Minnesota law. He also ruled that interest began accruing when Woodland Creek gave written notice of its claim on August 6, 2019, rather than when repairs were completed.
The detailed version
- Woodland Creek Manor Homes Association, Inc. v. AmGUARD Insurance Company · No. 0:20-cv-01833
- Eric Tostrud
- Feb. 25, 2022
Background
Woodland Creek owns a 138-unit property that suffered extensive hail damage on August 5, 2019. Woodland Creek notified AmGUARD of the loss on August 6, 2019. The parties agreed that the storm damage was covered under the insurance policy, but disagreed about the amount AmGUARD owed.
The policy gave AmGUARD several payment or repair options, and AmGUARD apparently chose to repair, rebuild, or replace the damaged property. After applying a $607,200 deductible, AmGUARD made two payments: $1,132,200 on November 14, 2019, and $1,792,000 on March 23, 2020.
The parties could not agree on the amount of the loss. After the case was removed to federal court, the court compelled an appraisal. In May 2021, the appraisal panel determined that the actual-cash value of the repair costs was $2,452,181.85. It also issued two replacement-cost-value figures: $3,272,777.50 using 2019 pricing for all repairs, and $3,622,695.04 using 2019 pricing for completed repairs and 2021 pricing for repairs not completed when the appraisal occurred.
Issues and analysis
The court considered the parties’ competing motions for partial summary judgment. Summary judgment is a decision without a trial when there is no genuine dispute about a fact that could affect the result and the moving party is entitled to judgment under the law. The parties agreed that Minnesota law applied.
Replacement-cost measurement date
AmGUARD argued that replacement-cost value should be measured using 2019 prices, when the storm occurred. Woodland Creek argued that the value should be measured when repairs were made or, for unrepaired items, when the appraisal occurred.
The court rejected AmGUARD’s position. It distinguished a Minnesota case involving actual-cash value because that case relied on policy language tying actual-cash value to the time of loss. The AmGUARD policy did not similarly tie replacement-cost value to the loss date. The court also reasoned that replacement cost generally reflects the cost needed to put the insured in the position it would have occupied if the loss had not occurred, which may require using information available at the time of repair or replacement.
The court therefore entered summary judgment for Woodland Creek on this issue. For completed repairs, replacement-cost value will be based on the repair costs determined by the appraisal panel. For repairs not completed, replacement-cost value will be based on the 2021 pricing data the panel used.
Interest on amounts paid before appraisal
Woodland Creek sought pre-award interest under Minnesota Statutes § 549.09 on the appraisal award, including amounts AmGUARD had paid before the appraisal. AmGUARD argued that its earlier payments should be excluded from the interest calculation from the dates those payments were made.
The court followed its earlier reasoning that pre-award interest is owed on “pecuniary damages,” meaning monetary compensation for a loss, and that those damages are reduced by an insurer’s pre-appraisal payments. The court also reasoned that awarding interest on the full appraisal award without accounting for earlier payments could create excessive or windfall recoveries.
The court rejected AmGUARD’s separate argument that no interest could be due because its payments exceeded the appraisal panel’s actual-cash-value award. Interest could have accrued on the full award from August 6, 2019, until the first payment, and on the reduced amount until the second payment. Because the record did not provide enough information to determine whether the earlier payments covered any interest due on the actual-cash-value portion, the court denied that part of AmGUARD’s motion without prejudice, using the court’s stated term.
Interest on replacement-cost value
AmGUARD argued that interest on the replacement-cost portion should not begin until Woodland Creek completed the repairs, or that Woodland Creek could not recover that interest because the relevant repairs had not been completed.
The court rejected the argument that repair completion starts the interest period. Under Minnesota law, the interest clock began when Woodland Creek gave written notice of its claim, on August 6, 2019. The policy’s rule about when replacement-cost payment becomes due did not change when interest began accruing.
The court nevertheless ruled that Woodland Creek was not currently entitled to recover interest on the replacement-cost portion because, as far as the record showed, the damaged property included in that portion of the award had not been repaired or replaced. Woodland Creek would become entitled to that interest if and when it became entitled to payment of the replacement-cost award.
Disposition
AmGUARD’s motion for partial summary judgment was granted in part: Woodland Creek was not entitled to pre-award interest on amounts AmGUARD paid before the appraisal from the dates of those payments, and Woodland Creek could recover pre-award interest on the appraisal panel’s replacement-cost-value award only after completing the repairs included in that award. AmGUARD’s motion was denied in all other respects.
Woodland Creek’s motion for partial summary judgment was granted in part: replacement-cost value would be measured when repairs were made or at appraisal, rather than when the loss occurred, and pre-award interest would accrue from August 6, 2019, the date of written notice of the claim. Woodland Creek’s motion was denied in all other respects.
Judge Eric C. Tostrud also declined to certify the repair-completion interest question to the Minnesota Supreme Court, finding that existing state-law sources left little uncertainty.
Read the full 15-page opinion on CourtListener, the free public archive maintained by the Free Law Project.