In Re: George Washington Bridge Bus Station Development Venture LLC
- Alvin Hellerstein
- 1:20-cv-07257
- U.S. District Court · Southern District of New York
- 8
In Tutor Perini v. George Washington, Judge Hellerstein affirmed the Bankruptcy Court’s settlement order and its effect on issues fully litigated by the appellant.
Tutor Perini Building Corp. was bound by the Bankruptcy Court’s Settlement Order as to issues it had fully litigated in its objection, while the settlement parties and non-debtor parties were affected by the order’s limits on inconsistent claims.
What happened
In Tutor Perini Building Corp. v. George Washington Bridge Bus Station Development Venture LLC, the contractor appealed a Bankruptcy Court order approving a settlement and limiting claims inconsistent with that order. Tutor Perini argued that the Bankruptcy Court had gone beyond what was needed to approve the settlement.
The district court disagreed. It held that the Bankruptcy Court followed the required notice and hearing procedures, and that Tutor Perini was bound by the order because it had objected to the settlement and fully argued its claims. The order could therefore preclude relitigation of issues the Bankruptcy Court had actually decided, including whether Tutor Perini was a third-party beneficiary of the ground lease and had a right to assert a payment-cure claim.
Judge Alvin K. Hellerstein affirmed the Bankruptcy Court’s Settlement Order and instructed the Clerk of Court to terminate the case. The scheduled oral argument was canceled.
The detailed version
- In Re: George Washington Bridge Bus Station Development Venture LLC · No. 1:20-cv-07257
- Alvin Hellerstein
- Feb. 25, 2021
Background
George Washington Bridge Bus Station Development Venture LLC was developing a renovation project and had hired Tutor Perini Building Corp. as the general contractor. After the debtor’s financial condition worsened, it filed for bankruptcy protection and sought to sell and assign its rights under a ground lease for the project.
The debtor, New York City Regional Center, LLC, and the Port Authority of New York and New Jersey negotiated a settlement addressing disputes involving the ground lease and related claims. The debtor asked the Bankruptcy Court to approve the settlement under Rule 9019 of the Federal Rules of Bankruptcy Procedure. Tutor Perini filed the sole objection, arguing in part that it was a third-party beneficiary of the ground lease and that its rights and claims should remain unaffected.
The Bankruptcy Court approved the settlement. It also determined that Tutor Perini was not a third-party beneficiary of the ground lease and had no right to assert a payment-cure claim under Section 365 of the Bankruptcy Code. The Settlement Order allowed Tutor Perini to pursue claims in other courts against non-debtor parties only if those claims were not inconsistent with the Bankruptcy Court’s order, factual findings, or legal conclusions. Tutor Perini appealed that limiting language, not the Bankruptcy Court’s approval of the settlement itself.
Issue and standard of review
The issue was whether the Bankruptcy Court improperly expanded the Settlement Order by barring Tutor Perini from asserting claims or causes of action inconsistent with the order in other courts. The district court reviewed that legal question anew. It explained that approval of a settlement ordinarily would not be overturned unless the Bankruptcy Court’s decision was seriously mistaken or outside its permitted discretion, but the specific legal issue presented on appeal received de novo review.
Court’s reasoning
The district court held that the Bankruptcy Court had authority to issue orders necessary or appropriate to carry out the Bankruptcy Code. Rule 9019 permits a bankruptcy court to approve a compromise after notice and a hearing, and Rule 9014 requires reasonable notice and an opportunity to be heard when a party objects.
The court found that those procedures were followed. The parties received notice and an opportunity to address the settlement and Tutor Perini’s objection, and Tutor Perini acknowledged that the parties exchanged multiple rounds of written arguments. Because Tutor Perini used those procedures to object and fully present its position, it was bound by the Bankruptcy Court’s order approving the settlement and addressing the objection.
The court also applied the principle known as collateral estoppel, which prevents a party from relitigating an issue of fact or law that was actually and fully litigated, decided, and necessary to a valid final judgment. The Bankruptcy Court had considered and decided Tutor Perini’s third-party-beneficiary and payment-cure arguments in a detailed order. The district court therefore concluded that the Settlement Order’s possible preclusive effect extended beyond the settlement’s approval to issues necessarily litigated and decided in resolving Tutor Perini’s objection.
Disposition
Judge Alvin K. Hellerstein affirmed the Bankruptcy Court’s Settlement Order. The Clerk of Court was instructed to terminate the case, and the oral argument scheduled for March 10, 2021, was canceled.
Read the full 8-page opinion on CourtListener, the free public archive maintained by the Free Law Project.