Court, Explained
U.S. Federal District Courts
←Back to docket
S.D.N.Y.Procedural orderFiled Feb. 25, 2021

ZAROUR v. CHUBB & SON, INC.

Judge
John Cronan
Docket
1:15-cv-02663
Court
U.S. District Court · Southern District of New York
Pages
6
Civil ProcedureInsuranceMotion to Dismiss
In one sentence

In Zarour v. Chubb, Judge Cronan denied Pacific Indemnity’s dismissal motion and ordered a mold-damage appraisal within ninety days.

Who this affects

Simon Zarour and Lori Zarour must work with Pacific Indemnity Company to complete the reopened mold-damage appraisal within ninety days. Chubb & Son, Inc. had previously been dismissed from the case. The court denied Pacific Indemnity’s request to dismiss for lack of prosecution but warned that the action could be dismissed without further notice if the parties failed to meet the deadline.

What happened

In ZAROUR v. CHUBB & SON, INC., Simon and Lori Zarour alleged that the defendants failed to cover damage to their home from Superstorm Sandy. An appraisal awarded them $110,490.20, and the court later ordered the appraisal reopened to address mold damage.

The reopened appraisal never occurred for more than three years. Pacific Indemnity Company asked the court to dismiss the case because the Zarours had not pursued the appraisal. The Zarours argued that Simon’s bankruptcy filing had automatically paused the case, but they had not raised that issue earlier and did not explain the delay before the bankruptcy filing.

Judge Cronan denied the motion to dismiss for lack of prosecution. He ordered the parties to complete the reopened appraisal within ninety days and warned that the case could be dismissed without further notice if they failed to proceed diligently and meet the deadline.

The detailed version

For law students, journalists, and other readers who want the full reasoning

Case
ZAROUR v. CHUBB & SON, INC. · No. 1:15-cv-02663
Judge
John Cronan
Date
Feb. 25, 2021

Background

Simon Zarour and Lori Zarour sued Chubb & Son, Inc. and Pacific Indemnity Company over alleged insurance coverage for losses to their home caused by Superstorm Sandy on October 29, 2012. The case was initially filed in the District of New Jersey. The parties later agreed that Chubb & Son, Inc. would be dismissed and that the case would be transferred to the Southern District of New York.

In 2015, Judge Jed S. Rakoff granted Pacific Indemnity’s motion to require an insurance appraisal. The three-person appraisal panel awarded the plaintiffs $110,490.20. The plaintiffs then asked to reopen the appraisal because the panel had not determined whether the home suffered mold damage. On February 22, 2017, Judge Rakoff granted that request and ordered the appraisal panel to determine whether, and to what extent, the plaintiffs had covered losses from mold damage.

Motion and delay

After the case was reassigned to Judge Cronan in September 2020, the court ordered the parties to provide a joint status update. The parties did not meet the initial deadline. Pacific Indemnity reported that its appraiser had tried to arrange a mold inspection but received no response from the plaintiffs’ appraiser. Pacific Indemnity also stated that it had received no further communications from the plaintiffs, their appraiser, or their counsel.

The plaintiffs said that their appraiser and Pacific Indemnity’s appraiser disagreed and that their own appraiser had not responded to their attempts to contact him. They did not explain why they had not pursued the reopened appraisal since February 2017. Pacific Indemnity then moved under Federal Rule of Civil Procedure 41(b) to dismiss for failure to prosecute, meaning failure to move the case forward.

The plaintiffs primarily argued that the reopened appraisal had not occurred because Simon’s March 2018 bankruptcy petition automatically stayed the case. Pacific Indemnity argued that the bankruptcy stay did not apply and that the plaintiffs had failed to prosecute the reopened appraisal. The opinion does not resolve the bankruptcy-stay issue as a separate ruling because the court denied the dismissal motion on other grounds.

Legal standard

A court may dismiss an action when a plaintiff fails to prosecute or fails to comply with court rules or a court order. Dismissal for failure to prosecute is a severe remedy that should be used only in extreme situations. The court considered the duration of the delay, whether the plaintiffs had notice that further delay could lead to dismissal, likely prejudice to the defendant, the need to manage the court’s calendar, the plaintiffs’ opportunity to have their claims heard, and whether a lesser sanction would be appropriate.

Court’s reasoning

The court found that the plaintiffs’ failure to take proactive steps to reopen the appraisal caused a significant delay of more than three years. The court also found likely prejudice to Pacific Indemnity because conducting an appraisal more than eight years after the property damage would be difficult. These considerations favored dismissal.

But the court emphasized that the plaintiffs had never been warned that further delay could result in dismissal. The court also found that both sides were at fault for failing to bring the appraisal problem to the court’s attention for more than three years. The court stated that Pacific Indemnity should have alerted the court or requested appropriate relief if the plaintiffs were obstructing the appraisal. Because dismissal would be a harsh remedy in these circumstances, the court concluded that a lesser resolution was appropriate.

Disposition

The court denied Pacific Indemnity Company’s motion to dismiss for lack of prosecution. It ordered the parties to complete the reopened appraisal required by Judge Rakoff’s February 22, 2017 order within ninety days after the February 25, 2021 order was filed. The court stated that it would not extend the deadline absent extremely good cause and that it could dismiss the action for failure to prosecute without further notice if the plaintiffs did not work diligently and the parties did not meet the deadline. The clerk was directed to terminate the motion at Docket Number 57.

The authoritative version

Read the full 6-page opinion on CourtListener, the free public archive maintained by the Free Law Project.

Open opinion PDF →
Summary written with AI assistance. See how summaries are made. Spot something wrong? Tell us.