Arch Specialty Insurance Company v. TDL Restoration, Inc.
- Kenneth Karas
- 7:18-cv-06712
- U.S. District Court · Southern District of New York
- 24
In Arch Specialty v. TDL Restoration, Judge Karas partly granted Arch’s summary-judgment motion on unpaid insurance premiums and partly denied it.
Arch Specialty Insurance Company obtained summary judgment on the established portions of its breach-of-contract claim against TDL Restoration, Inc., but damages issues involving the Executive Supervision category remained unresolved. The court denied summary judgment on Arch’s account-stated claim.
What happened
Arch Specialty Insurance Company v. TDL Restoration, Inc. involved Arch’s claim that TDL failed to pay additional insurance premiums and related taxes and fees after an audit. Arch asked the court to decide the dispute without a trial.
The court found that TDL breached the insurance policy, but it found unresolved issues about whether and how to charge for an executive-supervision category added during the audit. Those issues affected the final damages amount. The court also denied summary judgment on Arch’s account-stated claim because it sought the same damages based on the same facts as the contract claim.
Judge Karas granted in part and denied in part Arch’s motion for summary judgment. The ruling established TDL’s liability for the contract breach except for the identified executive-supervision and damages issues, while leaving the account-stated claim unresolved on that motion.
The detailed version
- Arch Specialty Insurance Company v. TDL Restoration, Inc. · No. 7:18-cv-06712
- Kenneth Karas
- Mar. 31, 2021
Background
Arch issued TDL a commercial general liability insurance policy covering March 28, 2016, through March 28, 2017. The initial premium was based on estimated exposure and the policy allowed an audit based on actual exposure during the coverage period. After an audit, Arch determined that TDL owed $171,339 in additional premium and claimed that TDL also owed $6,476.61 in New York taxes and fees, for a total of $177,815.61.
Arch sued TDL for breach of contract, unjust enrichment, and account stated. Arch moved for summary judgment—a decision without a trial when no genuine dispute of important fact requires a trial—on the breach-of-contract and account-stated claims.
TDL initially relied on records that it believed showed payment. During additional discovery, however, TDL admitted that it could not find proof that it had paid the additional premium or taxes and fees and agreed to withdraw that defense. The records were identified as ledger reports from TDL’s insurance broker, not proof of payment.
Breach of Contract
The court held that the insurance policy existed and that Arch performed its obligations under it. The court also held that there was no genuine dispute that TDL failed to pay the amounts due under the policy, satisfying the breach element of Arch’s contract claim.
The remaining question concerned damages. Arch had to show how its audit established the earned premium. After the court found Arch’s original documentation difficult to understand, Arch submitted a supplemental declaration explaining its calculation. The court was able to verify most of the calculation.
The court identified a problem involving an Executive Supervision category added in the audit. The audit report listed $27,500 in actual exposure for that category, but the audit endorsement combined that amount with New York Carpentry exposure and applied the New York Carpentry rates. The policy did not contain the Executive Supervision category or negotiated rates for it. The court held that Arch could not unilaterally decide how to charge for that additional category without properly modifying the contract and obtaining the required agreement.
Because Arch had not established that there was no genuine dispute about the damages amount, the court partially granted and partially denied summary judgment on the breach-of-contract claim. Summary judgment was granted on all aspects of that claim except these issues:
- whether TDL was liable for the Executive Supervision exposure; - what rate would apply if TDL were liable for that exposure; and - the total damages amount in light of those issues.
The court stated that, if the $27,500 Executive Supervision exposure were omitted, TDL would still owe $158,157 in additional premium and $5,978 in taxes and fees. It said it was prepared to amend the order and enter summary judgment for $164,135 if Arch chose to accept that calculation rather than continue litigating the additional exposure. The opinion does not state that the court entered that amended judgment.
Account-Stated Claim
An account stated is a claim based on a debtor’s alleged agreement that a particular amount is due. The court explained that such a claim cannot be used as another way to collect a disputed debt under the same contract.
The court found that Arch’s account-stated claim arose from the same facts and sought the same damages as its breach-of-contract claim. Because the claims were duplicative, the court concluded that TDL could not be held liable on both claims. The court therefore denied summary judgment on Arch’s account-stated claim.
Disposition
Judge Kenneth M. Karas concluded that Arch’s motion for summary judgment was granted in part and denied in part. The court granted summary judgment on the established portions of the breach-of-contract claim, left the Executive Supervision and related damages issues for further resolution, and denied summary judgment on the account-stated claim. The Clerk was directed to terminate the pending motion.
Read the full 24-page opinion on CourtListener, the free public archive maintained by the Free Law Project.
Related cases
- Arch Specialtyv. TDL Restoration
- Homesite Insurance Company, Argonaut Insurance Company, and Ironshore Indemnity…Aug 2026
- Grossv. Scottsdale Insurance
- Kaiser Foundation Health Plan, Inc., et al. v. National Union Fire Insurance…Aug 2026
- United Nationalv. Elite Ready-Mix
- Bloomington Lincoln Mercury Inc. d/b/a Lincoln of Bloomington v. Clear Blue…Jun 2026