Brian Trematore Plumbing & Heating, Inc. v. Walsh Construction Group, LLC
- Kenneth Karas
- 7:19-cv-09764
- U.S. District Court · Southern District of New York
- 14
In Brian Trematore v. Walsh, Judge Karas dismissed two claims without prejudice but denied dismissal of the quantum-meruit claim.
Brian Trematore Plumbing & Heating, Inc. may continue pursuing its quantum-meruit claim and may amend its defective-design and negligent-misrepresentation claims within 30 days. Walsh Construction Group, LLC and Consigli Construction Co., Inc. obtained dismissal of those two claims without prejudice.
What happened
Brian Trematore Plumbing & Heating, Inc. sued Walsh Construction Group, LLC and Consigli Construction Co., Inc. over a construction subcontract, asserting claims including defective design, quantum meruit, and negligent misrepresentation. Defendants asked the court to dismiss those three claims.
The court ruled that the defective-design claim did not adequately allege that Defendants controlled the project’s design. It also found that the negligent-misrepresentation claim did not identify specific false statements. But the court allowed the quantum-meruit claim to continue because the validity of the subcontract remained disputed, and quantum meruit could be available if the subcontract were found invalid or rescinded.
In Brian Trematore Plumbing & Heating, Inc. v. Walsh Construction Group, LLC, Judge Kenneth M. Karas granted Defendants’ motion to dismiss in part and denied it in part. The defective-design and negligent-misrepresentation claims were dismissed without prejudice, and Plaintiff may amend those claims within 30 days; dismissal of the quantum-meruit claim was denied.
The detailed version
- Brian Trematore Plumbing & Heating, Inc. v. Walsh Construction Group, LLC · No. 7:19-cv-09764
- Kenneth Karas
- Mar. 31, 2021
Background
Brian Trematore Plumbing & Heating, Inc. sued Walsh Construction Group, LLC and Consigli Construction Co., Inc. concerning a subcontract for plumbing work on a medical-center construction project. Plaintiff alleged breach of contract, quantum meruit, negligent misrepresentation, trust-fund diversion, cardinal change, and constructive contract rescission. Defendants moved under Federal Rule of Civil Procedure 12(b)(6), which tests whether a complaint alleges enough facts to state a legally plausible claim.
The motion addressed only three claims: breach of contract based on defective design, quantum meruit, and negligent misrepresentation. Plaintiff alleged that the project design was below the level required by the subcontract and contained numerous defects, that it performed work covered by unapproved change orders, and that Defendants negligently misrepresented the project’s design, sequencing, scheduling, and coordination.
Court’s Analysis
Defective-design claim. The court dismissed this claim because Plaintiff did not allege that Defendants controlled the project’s design or had contractually agreed to guarantee job performance. The court relied on New York law stating that, absent a contractual commitment otherwise, a prime contractor is not responsible for subcontractor delays unless they were caused by circumstances under the prime contractor’s direction or control. The court also concluded that the subcontract provisions cited by Plaintiff did not show that Defendants were responsible for design defects.
The court emphasized that its ruling was limited. It did not decide whether allegations about Defendants’ failure to approve change orders, wasteful instructions, or failure to respond to notices of design defects could support other claims.
Quantum-meruit claim. Quantum meruit is a theory allowing recovery for the value of work performed when an enforceable contract does not govern the disputed subject. Defendants argued that the subcontract barred this claim. The court declined to dismiss it because Plaintiff’s other claims alleged that the subcontract was invalid or had been constructively rescinded. At this early stage, the court allowed Plaintiff to plead quantum meruit as an alternative theory while the validity and scope of the subcontract remained disputed.
Negligent-misrepresentation claim. The court dismissed this claim because Plaintiff did not identify specific incorrect statements by Defendants. Allegations that Defendants misrepresented the project’s design, sequencing, scheduling, and coordination were too general. The court said Plaintiff needed to identify the statements on which the claim was based, even assuming that the heightened pleading standard for fraud did not apply. Because the claim failed for lack of specific alleged statements, the court did not address Defendants’ separate argument that Plaintiff had not alleged a duty independent of the subcontract.
Disposition
In Brian Trematore Plumbing & Heating, Inc. v. Walsh Construction Group, LLC, Judge Kenneth M. Karas granted in part and denied in part Defendants’ motion to dismiss. The motion was granted as to the defective-design and negligent-misrepresentation claims, and those claims were dismissed without prejudice because this was the first adjudication of them. The motion was denied as to Plaintiff’s quantum-meruit claim. Plaintiff was permitted to file an amended complaint within 30 days of the Opinion and Order. The court also scheduled a conference for June 8, 2021, at 10:00 a.m., and directed the Clerk to terminate the motion.
Read the full 14-page opinion on CourtListener, the free public archive maintained by the Free Law Project.