Court, Explained
U.S. Federal District Courts
←Back to docket
S.D.N.Y.Procedural orderFiled Dec. 2, 2021

Stoncor Group, Inc. v. Peerless Insurance Company

Judge
Gabriel Gorenstein
Docket
1:16-cv-04574-LAK-GWG
Court
U.S. District Court · Southern District of New York
Pages
11
Civil ProcedureEvidenceInsuranceContract
In one sentence

In Stoncor v. Peerless, Judge Gorenstein denied both motions in limine, allowing evidence about ongoing installation work and a later flooring project.

Who this affects

Stoncor Group, Inc. and First Continental Insurance Company, as the plaintiffs whose evidence was allowed, and Peerless Insurance Company, whose evidence was also allowed and whose motion to exclude the later-project evidence was denied.

What happened

Stoncor Group, Inc., doing business as Stonhard Corp., and First Continental Insurance Company sued Peerless Insurance Company over insurance coverage connected to a personal-injury lawsuit involving a floor at the Grand Hyatt Hotel. The parties asked the court to exclude evidence about whether Surfacesys’s work was finished when the accident occurred and about a later project that changed the floor’s texture.

Stoncor asked to exclude evidence about whether Surfacesys’s work was ongoing. Peerless asked to exclude evidence about the later project and about whether Surfacesys’s work was ongoing or complete. The earlier ruling in the case had found factual questions about whether the work was complete and whether an insurance-policy provision covering ongoing operations applied.

Judge Gorenstein denied both motions in limine. He ruled that the evidence about whether the work was ongoing was relevant and that the later project could help a factfinder decide whether Surfacesys’s operations were ongoing under the policy. He also ruled that the defense based on delay, the rule concerning later corrective measures, and the argument that the evidence would unfairly confuse the factfinder did not justify excluding it.

The detailed version

For law students, journalists, and other readers who want the full reasoning

Case
Stoncor Group, Inc. v. Peerless Insurance Company · No. 1:16-cv-04574-LAK-GWG
Judge
Gabriel Gorenstein
Date
Dec. 2, 2021

Background

Cesar Arias sued Stoncor in New York state court, alleging that he slipped and fell on a floor at the Grand Hyatt Hotel on September 19, 2006. An amended complaint also named Surfacesys, Inc. The opinion states that Stoncor manufactured the floor and Surfacesys installed it.

Surfacesys was the named insured under a commercial general liability policy issued by Peerless. Stoncor argued that an agreement with Surfacesys made Stoncor eligible for additional-insured coverage if specified conditions were met. The policy covered an additional insured only for liability arising from Surfacesys’s ongoing operations performed for that person or organization, and it excluded certain injuries occurring after covered work had been completed.

Stoncor asked Peerless to defend and indemnify it in the Arias lawsuit. Peerless did not provide coverage. First Continental paid Stoncor’s defense costs under a different insurance policy. Stoncor then sued Peerless for indemnity and for the costs, attorney’s fees, and expenses of defending the state-court action. The opinion states that the state-court action later ended after the Appellate Division granted summary judgment for Stoncor and Surfacesys and dismissed that action.

In an earlier ruling in this case, Judge Kaplan denied both sides’ summary-judgment motions. That ruling found factual questions about whether an executed agreement made Stoncor eligible for coverage and whether Stoncor’s and Surfacesys’s operations were complete before the accident. The court later dismissed the plaintiffs’ request for a declaration because the state-court action’s resolution eliminated the need for prospective relief, but it denied Peerless’s request to dismiss Stoncor as a party.

The Motions in Limine

A motion in limine asks the court to decide before trial whether particular evidence may be presented. The court stated that such evidence should be excluded only when it is clearly inadmissible on every possible ground.

Stoncor’s motion sought to exclude evidence concerning whether Surfacesys’s work was completed when the accident occurred. The evidence included Stoncor’s job file, related documents, and testimony from current and former Stoncor employees and Surfacesys’s former president. Peerless intended to use the evidence to argue that Surfacesys’s work was no longer ongoing and that Peerless therefore had no duty to defend.

Stoncor argued that the duty to defend should be decided only from the allegations in the underlying state-court complaint, which did not allege that the work was completed. The court rejected this argument for purposes of the motion. It concluded that Judge Kaplan’s earlier finding of a factual question about whether the operations were complete could not be reconciled with excluding all evidence on that subject. Because the earlier ruling was the law of the case—the principle that a court generally follows its earlier ruling on an issue in the same case—the court denied Stoncor’s motion.

Peerless’s motion sought to exclude evidence concerning a later project in which Surfacesys, working for Stoncor, refinished the floor with a different texture. Peerless argued that the evidence could confuse or mislead the factfinder, constituted evidence of a later corrective measure, and was barred by laches, an equitable defense based on unreasonable delay that prejudices the opposing party.

Ruling

Judge Gorenstein denied Peerless’s motion. He ruled that laches did not apply because the plaintiffs asserted a breach-of-contract claim and laches is an equitable doctrine. He also stated that the rule concerning later corrective measures did not apply because the evidence was not being offered for one of that rule’s prohibited purposes, such as proving negligence.

The court further concluded that the later project was relevant under Federal Rule of Evidence 401 because it could make it more or less likely that Surfacesys’s operations were ongoing when the accident occurred. The court held that the evidence was not subject to exclusion under Rule 403 because its value was not substantially outweighed by unfair prejudice, confusion, misleading the factfinder, delay, or other listed concerns. Peerless remained free to argue that the later project was not part of the ongoing operations covered by the policy.

The court’s conclusion was that Peerless’s motion in limine and the plaintiffs’ motion in limine were each denied.

The authoritative version

Read the full 11-page opinion on CourtListener, the free public archive maintained by the Free Law Project.

Open opinion PDF →
Summary written with AI assistance. See how summaries are made. Spot something wrong? Tell us.