China Railway No. 10 Engineering Group Co. Ltd. v. Triorient, LLC
- Richard Berman
- 1:21-cv-05941
- U.S. District Court · Southern District of New York
- 7
In China Railway No. 10 Engineering Group Co. Ltd. v. Triorient, LLC, Judge Berman confirmed the arbitration award and denied without prejudice fees for confirmation.
China Railway received a court-confirmed judgment for the arbitration award and may submit a supported request for confirmation-proceeding fees and costs. Triorient is subject to judgment for the specified amounts, interest, and arbitration-related fees and costs.
What happened
China Railway No. 10 Engineering Group Co. Ltd. and Triorient, LLC entered a contract for the sale and delivery of HBI. Triorient paid $7,000,000 of the $7,778,265 purchase price but did not pay the remaining balance. An arbitrator later ordered Triorient to pay the balance, arbitration costs, and legal fees and expenses.
China Railway asked the court to confirm the arbitration award. Triorient did not appear in the court proceedings and did not ask the court to change or cancel the award. The court treated the unanswered petition as an unopposed request for summary judgment and reviewed the arbitrator’s decision and the submitted materials.
Judge Berman granted the petition and directed entry of judgment for $778,265, plus 9% annual interest from October 26, 2017, $74,300 in arbitration costs, and $93,247.80 in arbitration legal fees and expenses, with interest on those two amounts from December 11, 2020. He denied without prejudice China Railway’s request for fees and costs incurred in the court confirmation proceeding because it had not provided a specific amount or supporting time records, while allowing a later application.
The detailed version
- China Railway No. 10 Engineering Group Co. Ltd. v. Triorient, LLC · No. 1:21-cv-05941
- Richard Berman
- Jan. 14, 2022
Background
China Railway No. 10 Engineering Group Co. Ltd. is identified in the opinion as a Chinese corporation based in Jinan, China. Triorient, LLC is identified as an American corporation based in Darien, Connecticut. On September 4, 2017, the parties entered a contract for China Railway’s sale and delivery of approximately 30,000 metric tons of HBI for a purchase price of $7,778,265. The contract required disputes to be resolved through mandatory arbitration in New York, New York, and provided that the prevailing party would receive reasonable attorney’s fees and costs.
China Railway shipped the HBI on October 4, 2017. Triorient paid $7,000,000 on October 25, 2017, but did not pay the remaining $778,265. China Railway began arbitration on September 18, 2019. During nearly 14 months of arbitration, Triorient argued that it was entitled to reduce the price because the goods did not conform to the contract specifications.
Arbitration Award and Court Proceedings
On December 11, 2020, the arbitrator issued a 48-page final award. He found that Triorient had not proved that it was entitled to reduce the price and ordered it to pay China Railway $778,265, $74,300 in arbitration costs, and $93,247.80 in legal fees and expenses incurred during the arbitration. The award provided for 9% annual interest on the $778,265 from October 26, 2017, until payment, and 9% annual interest on the arbitration costs and arbitration legal fees and expenses from December 11, 2020, until payment.
China Railway filed a petition to confirm the award on July 15, 2021, under the parties’ contract, the Federal Arbitration Act, and the Convention on Recognition and Enforcement of Foreign Arbitral Awards. Triorient was served but did not appear, respond, or ask the court to vacate, modify, or correct the award.
The court explained that an unanswered petition to confirm an arbitration award is treated as an unopposed motion for summary judgment. Summary judgment is a decision entered when the record shows no material factual dispute requiring a trial. The court reviewed the arbitrator’s decision and the materials submitted by China Railway, and found no material issue of fact that the arbitrator had not already resolved. The court also found the arbitrator’s decision comprehensive, well-reasoned, and supported by documentary and testimonial evidence.
Ruling
The court granted the Petition to Confirm the Arbitration Award. It directed the Clerk of Court to enter judgment for China Railway in the following amounts:
- $778,265 under the contract, plus 9% annual interest calculated from October 26, 2017, until payment; - $74,300 in arbitration costs, plus 9% annual interest calculated from December 11, 2020, until payment; and - $93,247.80 in legal fees and expenses incurred during the arbitration, plus 9% annual interest calculated from December 11, 2020, until payment.
China Railway also requested attorney’s fees and costs incurred in bringing the court confirmation proceeding. The court stated that such an award could be available because Triorient had not complied with the arbitrator’s award. But China Railway had not requested a specific amount or submitted time records or other documentation showing the work performed and costs incurred. The court therefore denied without prejudice the application for fees and costs incurred in the confirmation proceeding. China Railway was permitted to submit a supported application by January 24, 2022, after which the court said it would determine reasonable fees and costs and issue a later ruling.
Read the full 7-page opinion on CourtListener, the free public archive maintained by the Free Law Project.
Related cases
- Trustees Of The New York City District Council Of Carpenters Pension Fund…Nov 2021
- Trustees Of The New York City District Council Of Carpenters Pension Fund…Oct 2021
- Trustees Of The New York City District Council Of Carpenters Pension Fund…Oct 2021
- Drywall Tapers and Pointers of Greater New York Local Union 1974, Affiliated…Jun 2021
- Absolute Nevadav. Grand Majestic
- District Council No. 9 International Union of Painters and Allied Trades…May 2021