E & T Skyline Construction, LLC v. Talisman Casualty Insurance Company, LLC
- Analisa Torres
- 1:19-cv-08069
- U.S. District Court · Southern District of New York
- 25
E & T Skyline v. Talisman: Judge Torres denied both sides’ summary-judgment motions after finding jurisdiction and factual disputes about a construction bond.
E & T Skyline Construction, LLC and Talisman Casualty Insurance Company, LLC remain in the litigation; the court did not decide Talisman’s ultimate liability under the performance bond.
What happened
E & T Skyline Construction, LLC sued Talisman Casualty Insurance Company, LLC to enforce a performance bond covering work by subcontractor NY Renaissance Corporation. Talisman argued that the federal court lacked authority to hear the case, while E&T sought a ruling that Talisman was liable under the bond.
The court rejected Talisman’s jurisdiction arguments, finding that Jeffrey Schaff remained Talisman’s sole member and that Talisman was therefore a Louisiana citizen, creating diversity with E&T’s New York and New Jersey citizenship. But the court found factual disputes about whether E&T had obstructed NYR’s work, failed to provide safe storage and access, and thereby defaulted under the subcontract.
The court denied both parties’ motions for summary judgment. Judge Torres also denied E&T’s request for judgment based on Talisman’s alleged delay in investigating the bond claim, finding that Talisman’s promptness and liability remained disputed.
The detailed version
- E & T Skyline Construction, LLC v. Talisman Casualty Insurance Company, LLC · No. 1:19-cv-08069
- Analisa Torres
- Mar. 2, 2022
Background
E & T Skyline Construction, LLC (E&T), the general contractor for a condominium project, entered into a subcontract with NY Renaissance Corporation (NYR) to supply and install windows. NYR and Talisman Casualty Insurance Company, LLC executed a $1,850,000 performance bond in E&T’s favor. The bond required Talisman to complete NYR’s work if NYR defaulted or materially breached the subcontract, but it also stated that Talisman’s obligations arose only if E&T was not itself in default.
After delays, E&T accused NYR of default and terminated the subcontract. E&T then demanded that Talisman act under the bond. Talisman investigated and denied liability, stating that E&T had failed to provide clean, accessible, organized, and safe conditions for installing and storing the windows. E&T sued to enforce the bond and later moved for summary judgment on Talisman’s liability. Talisman filed a cross-motion for summary judgment, arguing primarily that the court lacked subject-matter jurisdiction.
Jurisdiction
Talisman argued that diversity jurisdiction was absent for two reasons: it claimed that it had no members and was therefore “stateless,” or, alternatively, that its participants should be treated as its members and some shared citizenship with E&T. The court treated Talisman’s summary-judgment motion as a renewed motion to dismiss under Federal Rule of Civil Procedure 12(b)(1), which concerns subject-matter jurisdiction.
The court rejected both arguments. Under Nevada law, an LLC must have at least one member, and the court determined that Jeffrey Schaff remained Talisman’s sole member. The court concluded that the amendment labeling Schaff as Talisman’s manager did not validly withdraw or end his membership because the required withdrawal procedures had not been followed and no other applicable provision authorized that result. Because Schaff was a Louisiana citizen, Talisman was a Louisiana citizen for diversity purposes. E&T was a citizen of New York and New Jersey, so the court found complete diversity.
The court also held that Talisman’s participants were not its members for diversity purposes. The governing documents gave participants interests in the assets, profits, losses, and distributions of particular protected cells, not in Talisman’s general assets. The documents also distinguished participants from members and denied participants authority to bind or represent Talisman. The court therefore denied Talisman’s motion to dismiss for lack of subject-matter jurisdiction on both grounds.
E&T’s Liability Claim Under the Bond
The court denied E&T’s motion for summary judgment on liability because genuine disputes of material fact remained. The bond made Talisman’s obligations conditional on E&T’s not being in default under the subcontract. The subcontract required E&T to cooperate in scheduling and performing NYR’s work, provide suitable storage areas, and avoid hindering or obstructing NYR’s performance.
Talisman presented evidence that debris, protrusions, blocked access, and inadequate storage areas prevented or made unsafe the delivery and installation of the windows. E&T disputed those assertions and argued that NYR had failed to meet its delivery obligations. The court concluded that a reasonable jury could find either that E&T had defaulted by failing to provide safe and unobstructed delivery and storage areas or that NYR had defaulted. Because credibility decisions and conflicting versions of events belong to a jury, not the court on summary judgment, E&T was not entitled to judgment as a matter of law.
The court did not decide Talisman’s argument concerning impossibility because factual disputes first had to be resolved regarding whether Talisman’s bond obligations were triggered.
Timeliness of Talisman’s Investigation
E&T separately sought summary judgment by arguing that Talisman had defaulted under the bond by failing to decide E&T’s claim promptly. The bond required Talisman to investigate after receiving notice, arrange for completion or payment, or deny liability with reasons and reasonable promptness. It also provided that Talisman would be in default if it failed to proceed as required after receiving an additional written notice.
The court denied E&T’s motion on this ground. Talisman acknowledged E&T’s claim within five days and resolved it within approximately a month, and the court could not conclude on the record that this conduct was unreasonably slow. The court also found that E&T’s August 5 letters did not establish a bond default because Talisman had already begun investigating by that date. In any event, the bond did not require the court to enter summary judgment for E&T merely because Talisman might have acted too slowly, particularly while factual disputes remained about whether Talisman’s liability had been triggered.
Disposition
The court denied both E&T’s and Talisman’s cross-motions for summary judgment and directed the Clerk of Court to terminate the motions.
Read the full 25-page opinion on CourtListener, the free public archive maintained by the Free Law Project.