Court, Explained
U.S. Federal District Courts
←Back to docket
S.D.N.Y.Procedural orderFiled June 14, 2022

99 Wall Development Inc. v. Allied World Specialty Insurance Company

Judge
Ronnie Abrams
Docket
1:18-cv-00126
Court
U.S. District Court · Southern District of New York
Pages
5
Civil ProcedureSummary JudgmentContractInsurance
In one sentence

In 99 Wall Development v. Allied World, Judge Abrams denied Allied World’s request to file another summary-judgment motion.

Who this affects

99 Wall Development Inc. and Allied World Specialty Insurance Company; the ruling controlled whether Allied World could file another summary-judgment motion before trial.

What happened

99 Wall Development Inc. sued Allied World Specialty Insurance Company over insurance coverage for losses from water events during a rehabilitation and renovation project. Allied World sought permission to file another summary-judgment motion concerning whether the policy covered certain repair costs.

99 Wall opposed the request, arguing that the deadline for summary-judgment motions had passed and that its complaint had always included repair costs. It also argued that the remaining dispute over the amount and classification of damages was a factual issue for trial, not a new legal issue for summary judgment.

Judge Ronnie Abrams denied Allied World’s request to file an additional summary-judgment motion. The court stated that 99 Wall had raised repair costs earlier, that Allied World had already had an opportunity to seek summary judgment on them, and that any dispute over repair costs and delay damages could be resolved at trial.

The detailed version

For law students, journalists, and other readers who want the full reasoning

Case
99 Wall Development Inc. v. Allied World Specialty Insurance Company · No. 1:18-cv-00126
Judge
Ronnie Abrams
Date
June 14, 2022

Background

99 Wall Development Inc. brought an insurance dispute against Allied World Specialty Insurance Company, formerly known as Darwin National Assurance Company. The dispute involved losses from water events during a rehabilitation and renovation project. The parties had previously filed summary-judgment motions by a court-ordered deadline of September 14, 2020.

Allied World asked for permission to file another motion for summary judgment. According to 99 Wall’s response, Allied World claimed it had only recently learned that 99 Wall’s breach-of-contract claim included a demand for payment of its full repair costs. Allied World also asserted that the insurance policy presented an unresolved legal question about coverage for certain repair costs that had been described as “general conditions.”

Arguments and court’s explanation

99 Wall opposed another motion. It argued that its complaint had identified construction costs to repair the physical damage and that the court had previously recognized two parts of its claim: repair costs and costs connected to delays in completing the project. 99 Wall maintained that Allied World had already had an opportunity to seek summary judgment on repair costs and that allowing a late motion would cause unnecessary delay.

99 Wall also argued that the policy’s Rehabilitation and Renovation Endorsement provided broader coverage than the basic Builders Risk Form. The opinion text shows that 99 Wall made these policy arguments, but the ruling did not decide the disputed coverage issue on the merits.

The court stated that Allied World’s request to file an additional summary-judgment motion was denied. The court noted that 99 Wall had demanded payment for repair costs in its complaint and that Allied World had an opportunity to move for summary judgment on those costs in its initial motion. Although the court had previously noted that Allied World made payments for repair costs, it had not ruled that those costs were fully paid. To the extent the parties disputed whether particular damages were repair costs or delay damages, the court stated that they could resolve that issue at trial.

Disposition

The court denied Allied World’s request to file an additional motion for summary judgment. The provided opinion text does not clearly state a separate ruling on 99 Wall’s alternative request for an extension of the pretrial-filing deadlines.

The authoritative version

Read the full 5-page opinion on CourtListener, the free public archive maintained by the Free Law Project.

Open opinion PDF →
Summary written with AI assistance. See how summaries are made. Spot something wrong? Tell us.