Hebei Mighty Synthetic Rubber and Plastic Co. Ltd. v. Global Syn-Turf, Inc.
- Paul Engelmayer
- 1:21-cv-10674
- U.S. District Court · Southern District of New York
- 7
Hebei Mighty v. Global Syn-Turf: Judge Engelmayer granted summary judgment, confirmed the arbitration award, and entered a $471,213.46 judgment plus interest.
Hebei received a confirmed arbitration award and a court judgment for $471,213.46, plus award interest and post-judgment interest. Global Syn-Turf is subject to that judgment.
What happened
In Hebei Mighty Synthetic Rubber and Plastic Co. Ltd. v. Global Syn-Turf, Inc., Hebei asked the court to confirm an arbitration award after Global Syn-Turf did not respond. The award required payment of $471,213.46, plus interest.
The court treated Hebei’s request for a default judgment as a request for summary judgment and independently reviewed whether Hebei was entitled to judgment. It found that the arbitrator acted within the parties’ agreement and gave a sufficient explanation for the award.
Judge Paul A. Engelmayer granted Hebei’s motion, confirmed the award, and entered judgment for $471,213.46, plus interest required by the award and additional post-judgment interest under federal law. The court directed the Clerk to close the case.
The detailed version
- Hebei Mighty Synthetic Rubber and Plastic Co. Ltd. v. Global Syn-Turf, Inc. · No. 1:21-cv-10674
- Paul Engelmayer
- Feb. 8, 2023
Background
Hebei petitioned under section 9 of the Federal Arbitration Act to confirm an arbitration award issued by the International Centre for Dispute Resolution, a division of the American Arbitration Association. Hebei and Global Syn-Turf had entered an agreement concerning the manufacture, marketing, and sale of synthetic turf. The agreement included an arbitration clause.
Global Syn-Turf initiated arbitration in 2019. After proceedings that included discovery, virtual hearings, and written submissions, the arbitrator issued a final award on May 17, 2021. The award provided Hebei with $130,788 in contractual damages, $312,046.71 for arbitration costs and legal fees, $28,378.75 in reimbursement, and interest at nine percent per year on specified amounts beginning 30 days after the award until payment.
Hebei filed its petition to confirm the award on December 14, 2021. After Hebei served Global Syn-Turf, Global Syn-Turf did not respond or appear. Hebei then moved for default judgment. The court stated that it would treat the motion as one for summary judgment and gave Global Syn-Turf an opportunity to oppose it, but Global Syn-Turf still did not appear.
Court’s Analysis
The court explained that an arbitration award does not automatically become a court judgment. A court generally confirms an award unless it has been vacated, modified, or corrected, and judicial review is highly limited. Because Global Syn-Turf had not appeared, the court evaluated the request under the standards for summary judgment rather than entering judgment solely because of the nonappearance.
The court found that Hebei had shown there was no genuine dispute over any material fact. It concluded that the arbitrator acted within the authority granted by the parties and thoroughly explained the findings supporting the award. The court found at least a minimally sufficient legal basis for the arbitrator’s result and concluded that summary judgment was warranted.
Disposition
Judge Paul A. Engelmayer granted Hebei’s motion, confirmed the arbitration award, and entered judgment for $471,213.46, plus interest in accordance with the award. The court also awarded post-judgment interest from the date judgment was entered until payment under 28 U.S.C. § 1961(a). It directed the Clerk of Court to terminate the motion and close the case.
Classification
This is a substantive ruling because the court treated the request as summary judgment, reviewed the arbitration award under the applicable standard, and decided that Hebei was entitled to judgment confirming the award.
Read the full 7-page opinion on CourtListener, the free public archive maintained by the Free Law Project.