Dow Olefinverbund GmbH v. Synthos Schkopau GmbH
- Paul Engelmayer
- 1:25-cv-05529
- U.S. District Court · Southern District of New York
- 6
In Dow Olefinverbund GmbH v. Synthos Schkopau GmbH, Judge Engelmayer confirmed an unopposed arbitration award requiring Synthos to pay Dow for steam, interest, and fees.
Dow Olefinverbund GmbH obtained confirmation of the arbitration award. Synthos Schkopau GmbH is subject to the resulting judgment for unpaid steam charges, interest, legal fees and costs, and administrative fees, as described in the opinion.
What happened
Dow Olefinverbund GmbH asked the court to confirm an arbitration award against Synthos Schkopau GmbH. The dispute arose from Synthos’s alleged failure to fully pay Dow for steam supplied under their Site Services Agreement.
The arbitrators found that Synthos materially breached the agreement but that Dow also committed a non-material breach. They ordered Synthos to pay outstanding steam invoices, interest, legal fees and costs, and administrative fees, and to pay future invoices without setting off claims. Synthos did not oppose Dow’s request for confirmation.
In Dow Olefinverbund GmbH v. Synthos Schkopau GmbH, Judge Paul A. Engelmayer granted Dow’s unopposed request, confirmed the award, directed entry of judgment, terminated pending motions, and closed the case.
The detailed version
- Dow Olefinverbund GmbH v. Synthos Schkopau GmbH · No. 1:25-cv-05529
- Paul Engelmayer
- Aug. 7, 2025
Background
Dow Olefinverbund GmbH and Synthos Schkopau GmbH are German corporations. Dow operates a petrochemical facility in Schkopau, Germany, and Synthos operates a synthetic rubber plant at Dow’s facility. Under their Site Services Agreement, Synthos purchased steam from Dow. The agreement selected New York law and required disputes to be decided by arbitration in New York County before a single arbitrator under the International Arbitration Rules of the American Arbitration Association.
Dow began arbitration on May 16, 2022, alleging that Synthos had not fully paid for steam supplied under the agreement. Synthos asserted counterclaims alleging that Dow failed to exercise good industry practice. After a hearing and additional briefing, the arbitration tribunal issued a final award on December 31, 2024.
The Arbitration Award
The tribunal found that Synthos materially breached the agreement by failing to pay its steam invoices in full. It also found that Dow committed a non-material breach by failing to assert its rights more vigorously against the steam supplier. The tribunal denied Synthos’s remaining counterclaims.
The award required Synthos to pay Dow the remaining balance on steam invoices issued between December 2021 and the award date, with a discount to account for Dow’s non-material breach. It also required payment of pre-award and post-award interest, legal fees and costs, and administrative fees. Going forward, Synthos was required to timely pay the full amount of Dow’s steam invoices and could not set off claims against those payments.
Court’s Analysis
Dow filed this action seeking confirmation of the award. Synthos did not oppose the petition, and Dow represented that Synthos had agreed not to oppose it.
The court explained that arbitration awards are not automatically enforceable as court judgments. Under the Federal Arbitration Act, courts generally confirm an award unless it has been vacated, modified, or corrected. Because Synthos had not appeared to oppose confirmation, the court evaluated Dow’s request under the standards for summary judgment, which asks whether there is any genuine dispute over a material fact and whether the requesting party is entitled to judgment as a matter of law.
The court emphasized that it still had to review Dow’s submission even though the request was unopposed. The court found no material factual dispute, determined that the tribunal acted within the authority granted by the parties’ agreement, and found at least a barely colorable justification for the tribunal’s result.
Ruling and Judgment
Judge Paul A. Engelmayer confirmed the award in Dow’s favor. The court directed entry of judgment for the amount still unpaid for steam supplied between December 2021 and December 31, 2024, plus pre-award and post-award interest, legal fees and costs, and administrative fees. The court directed the Clerk of Court to enter judgment, terminate pending motions, and close the case.
Read the full 6-page opinion on CourtListener, the free public archive maintained by the Free Law Project.