UNITED STATES OF AMERICA v. WESTCHESTER FIRE INSURANCE COMPANY
UNITED STATES OF AMERICA, f/u/o/b PROFEX, INC. and PROFEX, INC. v. WESTCHESTER FIRE INSURANCE COMPANY, KIRLIN BUILDERS, LLC, LIBERTY MUTUAL INSURANCE COMPANY
- Nelson Roman
- 7:22-cv-00015
- U.S. District Court · Southern District of New York
- 18
In United States v. Westchester Fire, Judge Roman granted Defendants’ summary-judgment motion, denied Kirlin’s partial motion, and held Defendants entitled to reasonable attorneys’ fees.
Profex’s claims were resolved against Profex and in favor of Kirlin Builders, LLC, Liberty Mutual Insurance Company, and Westchester Fire Insurance Company. Kirlin’s counterclaim and third-party claim for $330,754.49 in completion costs were not resolved in its favor on summary judgment. Western Surety Company received judgment as the third-party defendant, and the Defendants were entitled to reasonable attorneys’ fees, with the amount to be determined later.
What happened
In United States of America, f/u/o/b Profex, Inc. and Profex, Inc. v. Westchester Fire Insurance Company, Profex sought payment for labor, materials, equipment, and proposed change orders on a construction project. Profex asserted breach-of-contract, payment-bond, and equitable-payment claims against Kirlin Builders, LLC, Liberty Mutual Insurance Company, and Westchester Fire Insurance Company. Kirlin also sought $330,754.49 in project-completion costs from Profex and Western Surety Company.
The court ruled that Profex’s contract claims were barred because Profex did not give the written dispute notices required by its subcontract and did not prove that Kirlin had waived that requirement. The court also rejected Profex’s equitable-payment claims because the valid subcontract covered the same work and payment issues. Kirlin’s request for summary judgment on its completion-cost claims was denied because a factual dispute remained about whether the claimed costs were caused by Profex’s alleged default.
Judge Nelson S. Roman granted Defendants’ motion for summary judgment in its entirety, denied Kirlin’s motion for partial summary judgment, directed judgment for the Defendants and Western Surety Company, and held the Defendants entitled to reasonable attorneys’ fees under the subcontract. A magistrate judge was referred the task of determining the reasonable amount of those fees.
The detailed version
- UNITED STATES OF AMERICA v. WESTCHESTER FIRE INSURANCE COMPANY · No. 7:22-cv-00015
- Nelson Roman
- Sept. 30, 2025
Background
Kirlin Builders, LLC entered into a prime contract with the United States for work at the Johnson Veterinary Clinic at West Point, New York, and subcontracted with Profex, Inc. for $6,212,787. The subcontract required written submissions and approval for change orders, required written notice of disputes within a reasonable time, and stated that an untimely claim would be treated as waived or abandoned. It also allowed Kirlin to terminate Profex after notice of default and an opportunity to cure, recover losses and damages caused by default, and seek reasonable attorneys’ fees.
The parties disputed responsibility for substantial project delays and the handling of proposed change orders. Kirlin attributed about 600 days of delay to Profex and terminated Profex for cause on November 10, 2021. Kirlin claimed $330,754.49 in completion costs. Profex disputed the alleged defaults, challenged the termination, and argued that Kirlin had waived or abandoned the subcontract’s written-notice requirements through its conduct.
Profex brought claims for breach of contract, quantum meruit—a claim seeking the reasonable value of services outside an enforceable contract—and claims against Kirlin’s sureties. Kirlin filed a counterclaim against Profex and a third-party contract claim against Western Surety Company. The parties filed competing summary-judgment motions under Federal Rule of Civil Procedure 56, which permits judgment without a trial when no genuine dispute over a material fact exists and the moving party is entitled to judgment as a matter of law.
Profex’s Claims
The court held that Section 19 of the subcontract was a strict condition precedent to Profex’s claims. In other words, Profex had to comply with the written-dispute-notice requirement before pursuing its disputed payment claims. Applying New York law, the court concluded that Profex did not strictly comply with that requirement and that the evidence did not establish an indisputable mutual waiver by Kirlin and Profex.
The court found that Profex’s affidavits and other materials did not create a genuine factual dispute about waiver. It also relied on testimony from Profex personnel acknowledging that formal written dispute notices had not been submitted. The court therefore held that Profex’s breach-of-contract claim was barred by the subcontract’s notice provision and did not reach Defendants’ additional arguments concerning that claim.
The court separately held that Profex’s quantum meruit claim failed as a matter of law because a valid, enforceable subcontract governed the same subject matter, including the work, payment, and proposed change-order procedures. The court rejected Profex’s argument that the subcontract had been effectively abandoned, finding that the record showed the agreement remained operative during the project.
The court also held that Profex’s unjust-enrichment theory was not included in the complaint and could not be added for the first time in opposition papers. In addition, the court stated that the theory would be barred even if properly pleaded because the enforceable subcontract governed the same subject matter.
Kirlin’s Partial Summary-Judgment Motion
The court denied Kirlin’s motion for partial summary judgment on its counterclaim against Profex and its third-party complaint against Western Surety Company. Although Kirlin presented a ledger summarizing alleged completion payments, it did not provide invoices or other evidence establishing that the payments were made to complete Profex’s work or directly resulted from Profex’s alleged breach. The court found a genuine dispute about whether some or all of the claimed costs resulted from Profex’s default, Kirlin employees’ errors, or work beyond Profex’s scope.
Attorneys’ Fees and Disposition
The court held that Defendants were entitled to reasonable attorneys’ fees for the motion on which they prevailed because the subcontract contained an express fee-shifting provision. It denied fees for Kirlin’s unsuccessful partial-summary-judgment motion. The parties were referred to Magistrate Judge Judith C. McCarthy for a hearing to determine the reasonable amount of fees.
Judge Nelson S. Roman granted Defendants Kirlin Builders, LLC, Liberty Mutual Insurance Company, and Westchester Fire Insurance Company’s motion for summary judgment in its entirety. He denied Kirlin’s motion for partial summary judgment concerning Kirlin’s counterclaim and third-party complaint. The court directed the Clerk to enter judgment for those Defendants and for Western Surety Company, and to terminate the main action, counterclaim, third-party action, and motion at ECF No. 105. The conclusion identifies the proposed change-order numbers for which Defendants were entitled to summary judgment: 1–65, 75–86, 88–89, 92, 98, 100–107, 117, 123–125, 131, 134, 136, 138–144, 148–149, 151–152, 157, 161–168, 172–174, 176, 178–183, 186, and 189.
Read the full 18-page opinion on CourtListener, the free public archive maintained by the Free Law Project.
Related cases
- United States of America, f/u/o/b Profex, Inc. and Profex, Inc. v. Westchester…Oct 2025
- Drywall Tapers and Painters of Greater New York Local Union 1974, Affiliated…Sep 2025
- WFCM 2016-LC25v. Tyler
- Trustees of the District Council No. 9 Painting Industry Insurance Fund v…Jul 2025
- Trustees Of The New York City District Council Of Carpenters Pension Fund…Jun 2025
- District Council of New York City and Vicinity of the United Brotherhood of…Jun 2025