United States of America v. Westchester Fire Insurance Company
United States of America, f/u/o/b Profex, Inc. and Profex, Inc. v. Westchester Fire Insurance Company, Kirlin Builders, LLC, Liberty Mutual Insurance Company
- Nelson Roman
- 7:22-cv-00015
- U.S. District Court · Southern District of New York
- 19
United States v. Westchester Fire: Judge Roman granted defendants summary judgment, dismissed Profex’s claims, and denied Kirlin’s partial summary-judgment motion.
Profex’s claims against Kirlin Builders, LLC, Liberty Mutual Insurance Company, and Westchester Fire Insurance Company were dismissed, and judgment was directed in favor of those defendants. Kirlin’s counterclaim against Profex and third-party action against Western Surety Company remained open after Kirlin’s partial-summary-judgment motion was denied.
What happened
In United States of America, f/u/o/b Profex, Inc. and Profex, Inc. v. Westchester Fire Insurance Company, Kirlin Builders, LLC, and Liberty Mutual Insurance Company, Profex sought payment for construction work and proposed change orders on a project at West Point. Kirlin blamed Profex for delays and other failures, terminated the subcontract, and sought completion costs from Profex and Western Surety Company.
The court granted the defendants’ summary-judgment motion in its entirety. It ruled that Profex’s contract claims were barred because Profex did not give the written dispute notices required by the subcontract, and that Profex had not shown Kirlin clearly waived that requirement. The court also ruled that the valid subcontract barred Profex’s quantum-meruit and unjust-enrichment theories. The court dismissed Profex’s claims, without stating whether the dismissal was with or without prejudice.
Judge Nelson S. Roman denied Kirlin’s motion for partial summary judgment on its counterclaim and third-party claims because a factual dispute remained about whether the claimed completion costs were caused by Profex’s default. The court awarded defendants reasonable attorneys’ fees for their successful summary-judgment motion, referred the amount to Magistrate Judge Judith C. McCarthy, directed the clerk to enter judgment for the defendants on Profex’s claims, and directed the clerk to reopen the counterclaims and third-party action.
The detailed version
- United States of America v. Westchester Fire Insurance Company · No. 7:22-cv-00015
- Nelson Roman
- Oct. 10, 2025
Background
Kirlin Builders, LLC, the general contractor, subcontracted with Profex, Inc. for repair and renovation work at the Johnson Veterinary Clinic at West Point, New York. The subcontract was governed by New York law and included procedures for payment, change orders, disputes, default, termination, and attorneys’ fees.
Profex asserted claims for breach of contract, quantum meruit, and action on surety bonds, seeking payment for labor, materials, equipment, and proposed change orders. Kirlin claimed that Profex caused substantial delays, failed to address notices of default and notices to cure, failed to pay subcontractors and suppliers, and abandoned the work. Kirlin terminated Profex for cause and later sought $330,754.49 in completion costs through a counterclaim against Profex and a third-party action against Western Surety Company.
Profex’s claims
The court granted the defendants’ motion for summary judgment. It held that Section 19 of the subcontract created a strict notice condition: Profex had to provide written notice of a dispute within a reasonable time, or the claim would be treated as waived or abandoned. The court concluded that Profex did not strictly comply with this requirement and did not present clear evidence that Kirlin had waived it. Because the notice requirement barred Profex’s breach-of-contract claim, the court did not reach the defendants’ additional arguments on that claim.
The court also ruled that Profex’s quantum-meruit claim failed because a valid, enforceable subcontract governed the same subject matter. Quantum meruit is an equitable claim seeking the reasonable value of services, but the court explained that New York law does not allow that remedy when an express contract covers the parties’ work and payment. The court likewise barred any unjust-enrichment theory because it was not pleaded in the complaint and, in any event, was foreclosed by the valid subcontract.
Kirlin’s counterclaim and third-party action
The court denied Kirlin’s motion for partial summary judgment on its counterclaim against Profex and its third-party complaint against Western Surety Company. Kirlin relied on a ledger to support its claimed completion costs, but the court found that Kirlin had not provided invoices or other evidence establishing that the costs were incurred to complete Profex’s work or were directly caused by Profex’s alleged default. The court therefore found a genuine factual dispute about whether some or all of the claimed damages resulted from Profex’s default, Kirlin employees’ errors, or work beyond the scope of Profex’s obligations.
Attorneys’ fees and disposition
The court held that the defendants were entitled to reasonable attorneys’ fees for their successful motion for summary judgment under the subcontract’s fee-shifting provision. It ruled that fees were not recoverable for Kirlin’s denied partial-summary-judgment motion. The parties were referred to Magistrate Judge Judith C. McCarthy for a hearing to determine the amount of reasonable fees.
Judge Nelson S. Roman directed the clerk to terminate the main action and enter judgment for Kirlin, Liberty Mutual Insurance Company, and Westchester Fire Insurance Company against Profex. The court dismissed Profex’s causes of action and listed the proposed change orders on which the defendants obtained summary judgment. The court also directed the clerk to reopen Kirlin’s counterclaims and third-party action after reviewing Kirlin’s motion for correction or clarification, and directed the relevant parties to appear by teleconference on December 3, 2025. The opinion’s final scheduling paragraph is incomplete in the provided text, so its precise stated purpose cannot be determined from that paragraph alone.
Read the full 19-page opinion on CourtListener, the free public archive maintained by the Free Law Project.
Related cases
- UNITED STATES OF AMERICA, f/u/o/b PROFEX, INC. and PROFEX, INC. v. WESTCHESTER…Sep 2025
- Drywall Tapers and Pointers of Greater New York Local Union 1974, Affiliated…Jun 2021
- Drywall Tapers and Painters of Greater New York Local Union 1974, Affiliated…Sep 2025
- WFCM 2016-LC25v. Tyler
- Trustees of the District Council No. 9 Painting Industry Insurance Fund v…Jul 2025
- Trustees Of The New York City District Council Of Carpenters Pension Fund…Jun 2025