Court, Explained
U.S. Federal District Courts
←Back to docket
S.D.N.Y.Procedural orderFiled Feb. 14, 2020

Stoneway Capital Corporation v. Siemens Energy Inc.

Judge
George Daniels
Docket
1:19-cv-11355
Court
U.S. District Court · Southern District of New York
Pages
3
Civil ProcedurePreliminary InjunctionArbitration
In one sentence

In Stoneway Capital v. Siemens Energy, Judge Daniels denied both sides’ requests for emergency relief supporting arbitration.

Who this affects

Stoneway Capital Corporation and Siemens Energy Inc.; the order also concerned proposed communications with nonparty Bank of New York Mellon.

What happened

Stoneway Capital Corporation sued Siemens Energy Inc. and asked the court for an order supporting arbitration over the parties’ rights and obligations under a construction contract. Stoneway sought an order requiring notice before communications with Bank of New York Mellon and stopping Siemens from sending further default notices to that bank.

Siemens separately asked for an order temporarily preventing Stoneway from transferring assets and for an attachment of those assets while the court considered its request. The court explained that both sides had to satisfy the standards for emergency relief, and that Siemens also had to meet New York’s requirements for an attachment before judgment.

The court denied both Stoneway’s and Siemens’s motions, denied Stoneway’s request to file a later reply, and directed the clerk to close the motions and the case. Judge George B. Daniels found that Stoneway had not shown likely irreparable harm and that Siemens had not sufficiently shown insolvency, bankruptcy, or that a future arbitration award would be ineffective without relief.

The detailed version

For law students, journalists, and other readers who want the full reasoning

Case
Stoneway Capital Corporation v. Siemens Energy Inc. · No. 1:19-cv-11355
Judge
George Daniels
Date
Feb. 14, 2020

Background

Stoneway Capital Corporation brought the action against Siemens Energy Inc. seeking injunctive relief in support of arbitration concerning the parties’ rights and obligations under an Amended and Restated Turnkey Construction Contract. Stoneway moved for a preliminary injunction requiring the parties to provide notice to each other when communicating with nonparty Bank of New York Mellon, which served as collateral agent under a series of agreements. Stoneway also sought to stop Siemens from providing additional notices of default to Bank of New York Mellon while arbitration was pending.

Siemens later moved for an order of attachment and a temporary restraining order. It sought to prevent Stoneway from transferring assets while the court considered Siemens’s request for attachment.

Legal standards

The court stated that a temporary restraining order and a preliminary injunction use the same standard. The moving party must show a likelihood of success on the merits, likely irreparable harm without preliminary relief, that the balance of equities favors relief, and that an injunction serves the public interest.

The court also explained that federal law makes attachment available under the law of the state where the court is located. Under New York law, a party seeking attachment before judgment must show a cause of action, a probability of success on the merits, a statutory ground for attachment, and that the amount sought exceeds known counterclaims.

Court’s analysis and ruling

The court held that Stoneway had not met its burden for a preliminary injunction. In particular, it had not shown irreparable harm because arbitration had begun and there was no indication that Siemens intended to communicate further with Bank of New York Mellon about the alleged default notices. The court also noted that, during oral argument, Stoneway appeared to withdraw its motion and stated that it wanted the motion denied because the dispute-resolution process was underway in arbitration.

The court held that Siemens likewise had not met its burden for a temporary restraining order or attachment. Siemens had not sufficiently established Stoneway’s alleged insolvency or bankruptcy, or shown that a potential arbitration award would be ineffective without temporary relief.

Accordingly, the court denied both Stoneway’s and Siemens’s motions. The court also denied Stoneway’s request for permission to file a later reply concerning Siemens’s motion. The clerk was directed to close the motions and the case.

The authoritative version

Read the full 3-page opinion on CourtListener, the free public archive maintained by the Free Law Project.

Open opinion PDF →
Summary written with AI assistance. See how summaries are made. Spot something wrong? Tell us.