DK LIPA LLC v. Sybac Solar LLC
- Lorna Schofield
- 1:19-cv-01405
- U.S. District Court · Southern District of New York
- 10
In DK LIPA v. SB Energy, Judge Schofield denied Defendants’ motion to dismiss claims alleging that SB Energy failed to honor a contractual first-refusal right.
DK LIPA LLC’s breach-of-contract and tortious-interference claims against SB Energy Holdings, LLC and MISF, LLC were allowed to proceed past the motion-to-dismiss stage.
What happened
DK LIPA LLC sued SB Energy Holdings, LLC, formerly known as Sybac Solar LLC, and MISF, LLC, alleging breach of contract and tortious interference with contract. DK LIPA claimed that SB Energy should have notified it about a letter of intent and related arrangements concerning a solar project so DK LIPA could exercise a contractual right of first refusal.
The court held that the complaint plausibly alleged a breach of contract because the agreement could reasonably be read to treat the letter of intent as a written offer triggering that right. The court also held that the tortious-interference claim was sufficiently pleaded because Defendants’ challenge to that claim depended on their unsuccessful argument that no contract breach was plausibly alleged.
In DK LIPA LLC v. SB Energy Holdings, LLC (formerly known as Sybac Solar LLC), Judge Lorna G. Schofield denied Defendants’ motion to dismiss and directed the Clerk of Court to close the motion. The order did not resolve the claims after a trial or otherwise decide whether DK LIPA would ultimately prevail.
The detailed version
- DK LIPA LLC v. Sybac Solar LLC · No. 1:19-cv-01405
- Lorna Schofield
- June 4, 2020
Background
DK LIPA LLC sued SB Energy Holdings, LLC, formerly known as Sybac Solar LLC, and MISF, LLC. The claims alleged breach of contract and tortious interference with contract. Defendants moved to dismiss under Federal Rule of Civil Procedure 12(b)(6), which tests whether a complaint states a legally sufficient and plausible claim.
In 2013, DK LIPA and SB Energy entered into a Right of First Offer Agreement governed by New York law. The agreement concerned a planned 9.9-megawatt solar project on Long Island. After the agreement ended, Paragraph 8 required SB Energy, for 36 months, to notify DK LIPA within three business days of a written offer from another party. DK LIPA then had a one-time, 30-day right to enter into an engineering, procurement, and construction contract or purchase agreement on terms matching the other party’s terms, subject to a stated modification of the total consideration.
In 2016, SB Energy entered into a nonbinding letter of intent with MISF concerning partial co-development of a solar project known as Middle Island Solar Farm. The letter of intent referred to the same three power purchase agreements identified in SB Energy’s agreement with DK LIPA. It contemplated a jointly owned entity that would own, finance, and operate the project, lease the project site from MISF, and give MISF an option to purchase the project. SB Energy did not provide DK LIPA with the letter of intent or an opportunity to exercise a right of first refusal concerning the letter or related contracts.
Court’s Analysis
The court applied New York law. To state a breach-of-contract claim, DK LIPA had to plausibly allege an agreement, its own adequate performance, a breach by SB Energy, and resulting damages. The court focused on whether the complaint plausibly alleged a breach of Paragraph 8.
The court concluded that “written offer” could reasonably be understood to include the letter of intent. The agreement did not clearly limit that term to an offer to purchase the project or to a particular property. The project described in the letter of intent was also consistent with the agreement’s description because both concerned a solar project on Long Island, the same power purchase agreements, and the same intended power rating. The fact that the project was contemplated at a different location did not, based on the agreement’s text, establish that Paragraph 8 could not apply.
The court also rejected Defendants’ argument that the letter of intent involved a joint-venture structure fundamentally different from the purchase-and-construction arrangement contemplated by the agreement. The agreement could reasonably be read to support DK LIPA’s position that the project was the same project, moved to a different location, and that the arrangements were sufficiently similar for the letter of intent to trigger Paragraph 8. Because the contract was at least ambiguous on these points, the court was required at the motion-to-dismiss stage to resolve the ambiguity in DK LIPA’s favor.
The court separately held that the tortious-interference claim was sufficiently pleaded. That claim required, among other things, an actual breach of contract. Defendants disputed only that element and relied on their arguments against the breach-of-contract claim. Because the court found those arguments unpersuasive, it did not dismiss the tortious-interference claim.
Disposition
Judge Lorna G. Schofield denied Defendants’ motion to dismiss. The Clerk of Court was directed to close the motion at Docket Number 29. The opinion addressed only whether the complaint plausibly stated claims at the pleading stage; it did not determine the ultimate merits of those claims.
Read the full 10-page opinion on CourtListener, the free public archive maintained by the Free Law Project.